Cari Blog Ini

Jumat, 20 Januari 2012

The Regulation on Renewable Energies Power Plants

The Regulation on Renewable Energies Power Plants
Medium / Small  Scale Power Plants
Procurement Procedure
  • Ministerial regulation No 01/2006 on Procedure for Electric Power Purchase for Public Consumption
  • Ministerial Regulation No 2/2006 on Medium Scale Renewable Energies Based Power Plants
  • Ministerial decree No 1122/2002 on Scattered–Small Scale Scattered Power Plants
  • PKUK (Pemegang Kuasa Usaha Ketenagalistrikan = Holder of Attorney for Electrical Business) or PLN may purchase electricity from PIUKU/IPP by Tender or-by Direct Appointment (01/2006)
  • For Scattered Project Procurement for Small Scale Scattered Power Plants can be done by Direct Appointment (1122/2002)
         (1). Private Power Plants Maximum Capacity of 1 MW or
         (2). Excess Power Maximum Capacity of 1 MW
  • For Renewable Energy based Power Plants can be by Direct Appointment (01/2006 and 02/2006) :
         (1). Private Power Plants Minimum Capacity of 1 MW up to 10 MW or
         (2). Excess Power between 1 MW to 10 MW
  • Interested Parties may submit proposal (administrative and technical) to PLN with copies to Directorate General, Governor or Mayor of the Area (02/2006; 1122/2002)
  •  For Renewable Energy based Power Plants (as per 02/2006), Interested Parties can be : Joint Ventures, Privates, BUMD, Individual.
  • For Small Scale Scattered Power Plants; interested parties should be Small Business/Small Scale Privates Company/ Joint Ventures.
                               The Regulation on Renewable Energies Power Plants                             Small / Medium Scale Power Plants    
Tender Procedure

  •  Privates or Ventures interested must obtained License for Electrical Business for Public Consumption (fixed IUKU) (01/2006).
  •  For Medium Scale Minimum Term of Contract: 10 years (02/2006).
  • Construction can only be started after the license (fixed IUKU) is obtained (02/2006)
  • In carrying out the Project, Developers shall use / utilize domestic product/ services (02/2006).
  • Power Plants can be operated after obtaining Commissioning Certificate from authority decided by Government (02/2006)
  • For Small Scale Scattered Power Plants, Privates or Ventures interested must also obtained License for Electrical Business for Small Scale Scattered Power Plants (IUK PSK) (1122/2002).
  • The License is given after Privates obtaining the Commissioning Certificate (1122/2002) 
                             
                             
     

       
     

       
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     



             



             



         



       


                         

                       
     
     


       
       
       
     





     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
      Note :  - PKUK  = Pemegang Kuasa Usaha Ketenagalistrikan          
                           (Holder of Attorney for  Electrical Business )          
         - PIUKU  = Pemegang Izin Usaha Ketenagalistrikan untuk Kepentingan Umum      
                           (Holder of License for Electrical Business for Public Consumpsion)    
                             
    file : Arief Budiardjo                    